Shortly after Thomas and I decided to register team Sea Runners for the Race to Alaska (R2AK), we decided we should honor our boat-building experience — as well as James Wharram himself — by using the Wharram Hitia 17 design as the foundation of our race boat. Since Thomas is an architect and we both have built Wharrams (he a Tiki 26; me a Tiki 21), we hardly looked at the plans after laying out the hull sides and bulkheads. In fact, we’ve made a lot of modifications to keep the boat light and otherwise adapted to being powered by humans and the wind, rather than a motor. (The key rule of the R2AK = no motors!)
This post documents our 1-month build of the hulls — from plans to floating… First we present a fun build video that my son, Liam, put together during a “Tiki Tuesday” in a matter of mere minutes.
Below you’ll find a gallery of selected stills followed by the day-by-day build log. Enjoy!
This was a fun, fast build for us that made us feel confident that deciding to build a Wharram design with which we were familiar was a good strategy. We didn’t clock our hours exactly, but estimate it took us about at most 250 hours (42 days x 6 hours) the build time for the Hitia 17 advertised on the Wharram web site. (This confirms our suspicion that the build times and boat weights listed on the Wharram site are pretty ideal — maybe pie-in-the-sky. For non-expert builders, we advise multiplication by 1.5 for a more accurate estimates…)
Here’s a calendar of the build.
Tue 10/14 | Build started with the ceremony of the long tables & the death of a flagon of Pyrat (Thanks to our helpers Tim King and Erik Hvalsoe) |
Wed 10/15 | T drafts and cuts out bulkheads and hull side panels |
Thu 10/16 | T cuts out stem, stern, rudder, lashing backing plates |
Fri 10/17 | S cuts out butt blocks; T glues up hull sides with butt blocks |
Sun 10/19 | am: Thomas rips stringers, keel; late eve: Thomas staples outer scarfed stringers to hulls; S&T glue scarfed keels |
Mon 10/20 | Hulls zip tied and stood up with bulkheads in place. |
Tue 10/21 | T,S,&K align and glue hull B |
Thu 10/23 | T&S align and glue hull A |
10/27/2014 | Keel fillets, End foaming, aft storage locker and diagonals added |
11/1/2014 | Decks made and undersides coated. First spar mock up glued up. |
11/3/2014 | Glued in bunk stringers on hulls and at bulkheads |
11/4/2014 | Glued on cabin sides |
11/5/2014 | Kennewick/paper day |
11/6/2014 | Made bunk cross-stringers, sanded holds |
11/7/2014 | Fitting bunks, painting holds, filling holes and coating bunks. |
11/8/2014 | Glued on decks and fixed bunk boards (with Kevin after Kenmore ride/dip) |
11/9/2014 | Cleaned up fillets, made and fit cabin side stringers and aft coaming pieces |
11/10/2014 | Glued in cabin side stringers and aft coaming pieces; trimmed decks |
11/11/2014 | Make deck and coaming pieces. broke rear seat B loose (do we need glass tape at stress points?) |
11/12/2014 | Coat cabin deck pieces/sand decks/make rudder and handle doublers |
11/13/2014 | Glue up coaming to cabin deck |
11/14/2014 | Fillet underside of coaming. Later glue cabin deck to cabin |
11/15/2014 | Sand decks/cabins, flip to sand hulls, fair stem/stern, shape keel |
11/16/2014 | T&S stay up late to glass cabin ends & rudders |
11/17/2014 | T&S glass decks |
Tue 11/18 | T glasses cabin sides during day; T&S sand hulls, glass 1st side of hulls |
Wed 11/19 | S fills 1st side hulls and rudder weave w/epoxy coat #2 |
Th 11/20 | T & S sand and glass 2nd side of hulls; discuss lash pads & doublers; fill 2nd side rudders |
Fri 11/21 | T trims hull glass; S cleans up stringer for fillet, forms doublers & pads |
Sat 11/22 | S buys hardware for pads; T&S glue pads, kevlar bow, carbon fiber skeg, fillet stringer, glass keel. |
Sun 11/23 | First assembly! |
Mon 11/24 | Launch, paddle/flip/right/bail. We got it wet in 42 days (42×6 hours = 252hrs!) |